Project Management Consultant for the construction of the Pskem HPP dam in the Bostanlyk district of the Tashkent province. JSC Uzbekhydroenergo funds
Name of Client: Construction Directorate No. 4 of JSC Uzbekhydroenergo
Status: Ongoing
The project involves the construction of the Pskem Hydroelectric Power Plant on the Pskem River in the Bostanlyk District. The main parameters of the facility include the construction of a 125 m high rock-fill dam with a reinforced concrete screen, construction of an above-ground hydroelectric power plant building with four 100 MW hydroelectric units (total capacity 400 MW), and a deep spillway with a capacity of 280 m3/s. The construction will result in the creation of the Pskemskoye Reservoir with a volume of 511.2 million m3 for seasonal flow regulation.
Project Implementation Support Services:
establishment of the project management office;
preparation of tender documentation and Employer’s Requirements;
comprehensive support during the procurement of the turnkey contractor under FIDIC Silver Book, from bidder clarifications to bid evaluation and negotiations;
review and approval of the contractor’s design documentation and monitoring of construction schedules;
verification of IPCs and control of material and equipment compliance;
oversight of safety, quality and technical standards at the construction site;
supervision of major construction works and regular reporting to the Client.